Project Overview and Chronology of Events

PROJECT OVERVIEW

          The Jalaur River Multi-Purpose Project Stage II (JRMP II) is the first large-scale water reservoir to be constructed in the Visayas and Mindanao regions. In fact, it is the National Irrigation Administration’s (NIA) flagship project in Western Visayas. JRMP II aims to usher inclusive development among stakeholders achieved through harnessing the potential of the Jalaur River for multi-purpose benefit while minimizing feasible impacts to the environment and to the project-covered communities. Such benefits include year-round irrigation, bulk water supply, hydroelectric power, and eco- tourism among many others. Primary areas that shall be served by the project include the towns of Calinog, Lambunao, Badiangan, Janiuay, Cabatuan, Sta. Barbara, Pavia, Alimodian, Leon, San Miguel, Oton, Tigbauan, Duenas, San Enrique,  Anilao, Dingle, Barotac Nuevo, Dumangas, Mina, New Lucena, Pototan, Zarraga and Leganes, Passi City, and Iloilo City.

          JRMP was first implemented by NIA in 1960s after the Fourth Congress of the Philippines passed Republic Act 2651 (R.A. 2651) in June 18, 1960. The law provides for the construction of the Jalaur Multi-Purpose Project in the Province of Iloilo and governing its operation after its completion. The first phase of the project was completed in 1980s; its second stage commenced in 2012 after the National Economic Development Authority (NEDA) Board approved its second phase for its 16.26% Economic Internal Rate of Return (EIRR).

          For its second stage, the project involves three major components, Irrigation Development, Environmental and Watershed Management, and Institutional Development. For Irrigation Development, JRMP II covers the construction of three dams, all in Calinog Town, and a high line canal that will traverse nine towns of the province of Iloilo, from Calinog to Oton town. It will also rehabilitate and modernize existing National Irrigation Systems (NIS) in the province. Judicious execution of sound environmental plans and programs relative to JRMP II implementation is the major objective of the Environmental and Watershed Management component. Also, this component aims to protect and to preserve the forests to ensure water for the project. Further still, it involves securing an Environmental Compliance Certificate (ECC) from the Environmental Management Bureau (EMB) and creation of a Multi-Partite Monitoring Team (MMT) to monitor NIA’s compliance to environmental regulations and conditions of the ECC.  All plans relative to the environment and the watershed were prepared adhering to the result of the Environmental Impact Assessment (EIA) conducted for the project. The Institutional Component of JRMP II is provided under NIA Memorandum Circular (MC) 9 s. of 1986 which directs for the integration of the Institutional Development Program (IDP) within appropriate levels of the agency. This component aims to organize Irrigators’ Associations (IAs) in new irrigated areas generated by the project, and to strengthen existing IAs in the rehabilitated NIS. In addition, this component also covers the application of JRMP II for a Free Prior and Informed Consent (FPIC). This process is required by Republic Act 8371 (R.A. 8371) of the Indigenous Peoples Rights Act (IPRA) which ensures IPs approval for the construction activities within their inherited lands. The FPIC process is facilitated by the National Commission on Indigenous Peoples (NCIP). 

 

CHRONOLOGY OF EVENTS

Jun 1960                           

The JRMP came into being under Republic Act 2651. Stage I of the project involves the rehabilitation of irrigation systems covering an area of 22,340 hectares. Stage II involves the construction of a large-scale reservoir dam to provide uninterrupted irrigation water supply to 31,840 hectares of farmland.  

 

Jul 1982                            

Completion of JRMP Stage I

 

1982                                  

Proposed implementation of JRMP Stage II but project put on hold until 2009

 

Jul 2009                            

Re-conduct of feasibility study for JRMP II

 

Aug 2011                          

Conduct of Environmental Impact Assessment (EIA) by third-party consultant (SDS)

 

Oct 2011                           

Submission of feasibility study and endorsement to the National Economic and Development Authority (NEDA)

 

Mar 2012                          

Approval of JRMP II by NEDA

 

May 2012                         

Submission of EIA to the Environmental Management Bureau of the Department of Environment and Natural Resources (DENR-EMB)                       

Pledge of loan from the Economic Development Cooperation Fund (EDCF) of the Republic of South Korea

 

Jun 2012                           

Inauguration of JRMP II during the First International Iloilo River Summit

 

Jul 2012                            

Commencement of Social Preparation and other pre-implementation activities

Issuance of the Environmental Compliance Certificate (ECC) by the DENR

Issuance of Certification Pre-Condition for Feasibility Study by the National Commission on Indigenous Peoples (NCIP) in preparation for securing Free Prior Informed Consent (FPIC) for JRMP II

Public Consultation with various stakeholders in compliance with ECC guidelines

 

Sep 2012                          

Creation of the Information, Education and Communication (IEC) Committee led by the National Irrigation Administration (NIA)

 

Feb 2013                          

Ceremonial Groundbreaking of JRMP II led by President Benigno Aquino III and Senator Franklin Drilon

 

Sep 2013                          

First Pre-FPIC Conference where the NIA presented JRMP II plans and programs

 

Oct 2013                           

Commencement of Detailed Engineering and Construction Design                        

Conduct of Engineering Geological Geohazard Assessment (EGGA)

 

Nov 2013                         

Conduct of Socio-Economic and Cultural Survey (SECIA) covering nine (9) Indigenous Peoples (IP) communities

 

Apr 2014                          

Conduct of Stakeholders Forum where NIA presented the initial dam design, social and environmental impact of the project and how to mitigate them and the proposed Land Acquisition and Resettlement Action Plan  (LARAP)

 

Aug 2014                          

Release of final DED and LARAP

 

Oct 2014                           

Conduct of Pre-FPIC Orientation with the 393 Project Affected Families (PAFs)

 

Nov 2014                         

Conduct 3rd round of Pre-FPIC conference (Finalization of Work and Financial Plan and Schedules of Community Assemblies)

Start of FPIC process

 

Jan 2015                           

Commencement of negotiation with affected IP communities

 

Apr 2015                          

IP Elders representing all 16 affected barangays signify support for the project through signed MOAs

 

May 2015                         

Conduct of National Peoples’ Forum

 

 

* Preparation for the bidding for the construction of the project to commence upon receipt of the Certification Precondition from NCIP.